Financial Support

Industrial Complex Financial Support Programme

A government programme providing long-term, low-interest loans covering a substantial share of installation costs for companies installing renewable energy facilities on high-potential idle land and factory roofs within industrial complexes.
Industrial complex solar qualifies as “priority support”, with a support ratio 5 %p above the standard rate.

Eligibility

Eligibility

SMEs and mid-sized companies installing PV facilities individually or jointly (as a cooperative) on buildings or land within an industrial complex — including those leasing sites, factories or factory roofs to run a generation business

Detailed Conditions

For cooperatives, at least 70 % of members must be tenants of the industrial complex; general factories outside industrial complexes may also apply

★ Industrial complex solar = “priority support” — support ratio raised by 5 %p above the standard rate
Excludes the Green Innovation Finance Programme · annual rounds and notices

Support Conditions (as of 2026)

Interest Rate

Quarterly variable rate (per the Special Accounting Guidelines for Energy and Resources Projects, announced each quarter by the New & Renewable Energy Center)

Original wording “quarterly variable rate” retained

Loan Term

5-year grace period, 10-year instalment repayment

Total 15-year loan

Support Ratio (standard)

SMEs (including individuals and cooperatives) up to 75 % / mid-sized companies up to 55 % / RE100 large companies (self-consumption) up to 35 %

Of total project cost / Source: New & Renewable Energy Center financial support programme

Support Ratio (priority support)

Industrial complex solar qualifies for priority support → ratio raised by 5 %p: SMEs 80 % / mid-sized 60 % / RE100 large companies up to 40 %

★ Key 2026 update (industrial complex priority support +5 %p)

Support Limit

Up to KRW 30 billion per business operator in the solar sector
(minimum application KRW 30 million; recommendations in KRW 1 million units)

Source: New & Renewable Energy Center financial support programme

Low-Carbon Modules

Support requires the use of low-carbon PV modules emitting 655 kgCO₂/kW or less (mandatory)

★ Applies from 2026 (low-carbon module standard notified by the Ministry of Climate)

Required Documents & Application Period

Required Documents

Industrial Complex

Classified as national, general, urban high-tech or agro-industrial complex
(a tenancy certificate is required)

Industrial complexes designated under Articles 6–8 of the Industrial Sites Act

Factory

Factory registration certificate required

Building

Building register

Multi-owned Building

Consent of at least 80 % of sectional owners (by owned area) required

Application & Loan Procedure

  • STEP 01

    Programme announcement

    MOTIE / Center

  • STEP 02

    Online funding application

    Applicant → Center

  • STEP 03

    Review and evaluation for funding recommendation

    Center / Integrated
    Support Center

  • STEP 04

    Issuance of
    recommendation letter

    Center /
    Integrated Support Center
    → Applicant

  • STEP 05

    Progress payment / loan application and approval

    Applicant ↔ Bank

  • STEP 06

    Initial drawdown

    Bank ↔ Applicant

  • STEP 07

    Completion and final drawdown

    Bank ↔ Applicant

  • STEP 08

    Field inspection

    Center → Applicant

  • STEP 09

    Repayment

    Applicant →
    Bank → Center

Start your solar power generation project with NEOTEC ENC